Halls · Sulzfeld, Germany · 2026 –

Workshop & Machinery Hall · Schmitt Besitz GmbH

In Sulzfeld (Lower Franconia) we are building two halls for Schmitt Besitz GmbH: a workshop hall of around 1,050 sqm and a machinery hall of around 500 sqm. The client is a construction professional himself — an earthworks contractor whose machinery fleet will be maintained, repaired and stored here.

When a professional who earns his living on construction sites builds for his own operation, he examines his partner more closely than any other client. That is exactly what makes this project a special reference for us: a steel structure of European rolled sections, columns on pad foundations, bracing and purlin grid — all visible in the July 2026 site photos.

Construction started in April 2026 and the project is currently under way: since September 2026 the roof and wall envelope of both halls is closed, the workshop hall's floor slab has been poured with underfloor heating, and the fit-out follows. We will keep documenting the progress here — the gallery runs from the current state back to the beginning.

CONSTRUCTION RECORD

BOTH HALLS · ENVELOPE COMPLETE · SEPTEMBER 202601 / 40
MACHINERY HALL · OPEN LONG SIDE02 / 40
MACHINERY HALL · SANDWICH-PANEL FACADE03 / 40
MACHINERY HALL · MONO-PITCH ROOF WITH CANOPY04 / 40
MACHINERY HALL · FRAME AND ROOF SKIN05 / 40
WORKSHOP HALL INTERIOR · RIDGE LIGHT06 / 40
WORKSHOP HALL INTERIOR · FLOOR SLAB07 / 40
WORKSHOP HALL · FOUR SECTIONAL DOORS08 / 40
SITE SIGN · MACHINERY HALL09 / 40
ROOF · TRAPEZOIDAL SHEETING10 / 40
ROOFLIGHT AND SMOKE VENT · DETAIL11 / 40
MACHINERY HALL ERECTION · MOBILE CRANE12 / 40
PURLIN GRID · CRANE LIFT13 / 40
WORKSHOP HALL · FACADE CLOSED14 / 40
MACHINERY HALL FRAME · SITE SIGN15 / 40
BRACING · PURLINS · DETAIL16 / 40
STEEL SKELETON · VIEW TO WORKSHOP HALL17 / 40
BOTH HALLS · ERECTION · SEPTEMBER 202618 / 40
FLOOR SLAB · CONCRETE POUR19 / 40
UNDERFLOOR HEATING · REBAR20 / 40
STEEL FRAME COMPLETE · JULY 202621 / 40
FRAME WITH BRACING · JULY 202622 / 40
STEEL SKELETON COMPLETE23 / 40
ERECTION INSIDE · TELEHANDLER24 / 40
STEEL FRAME ERECTED · JULY 202625 / 40
ERECTION START · COLUMN ROW26 / 40
COLUMNS ON PAD FOUNDATIONS27 / 40
RAIL INSTALLATION · TELEHANDLER28 / 40
MOBILE CRANE · RAFTER LIFT29 / 40
FRAME ASSEMBLY · RIDGE30 / 40
MAIN FRAME · GABLE END31 / 40
MOBILE CRANE · FRAME STANDING32 / 40
BRACING · PAD FOUNDATIONS33 / 40
PURLIN GRID · INTERIOR34 / 40
STRIP FOUNDATION REBAR35 / 40
FOUNDATION WORKS36 / 40
REBAR CAGE · DETAIL37 / 40
FORMWORK · FOUNDATION BEAM38 / 40
STRIP FOUNDATION · REBAR39 / 40
FORMWORK AND REBAR40 / 40

Scroll to browse